Successful delivery of new packaging line at Enza in Enkhuizen
Early 2025, our existing customer ENZA Zaden approached us to replace an outdated packaging line consisting of a multihead weigher, platform, and vertical form, fill and seal (VFFS) machine.
Following the start of an extensive engineering process – featuring weekly online meetings between Enza Zaden, JASA Packaging Solutions, and our team – all technical details and interface points could be aligned at an early stage. After several budget rounds, the final quotation was issued in October 2025, resulting in the official order on November 1, 2025.
Thanks to this thorough preparation, we were able to start engineering and construction immediately. On April 20, 2026, the Factory Acceptance Test (FAT) was successfully completed at our workshop in Dongen. The system was then transported to JASA in Obdam, where the combined FAT with the new JASA packaging machine was successfully concluded on May 27, 2026.
After disassembly, transport, and reassembly in Enkhuizen, our service engineers commissioned the complete line together with the JASA team. Following a successful Site Acceptance Test (SAT) on June 17, 2026, the final points were addressed. With the official initial calibration (Nieuwkeuring) completed by Kalibra on Friday, August 14, 2026, the project was officially concluded.
We look back on a very pleasant collaboration with Enza and JASA and are proud of the result: a modern,future-proof packaging line. Thanks to everyone involved for their dedication!